The quotation tells you what you thought a job would make. Looking at the completed job tells you whether you were right.

To work out the profit properly, start with what the job actually brought in, then take away what it really cost to deliver, including the labour, other trades and job costs, along with the share of the business costs you have allowed for. What is left gives you a much better picture of what the job actually did for the business.

You do not need to turn every installation into an accounting project. You need enough information to compare what you priced with what really happened.

In this answer
  1. Use the real figures once you have them
  2. Look at what changed from the price
  3. Count the small bits of time as well
  4. The job can look different once everything is included
  5. Look for patterns rather than worrying about one job

Use the real figures once you have them

When you price a job, some of the numbers are estimates because the work has not happened yet. Once it is finished, you can use the actual invoice value, the electrician’s bill, the waste and materials costs, and the time the installation really took.

If there was properly agreed additional work, include the additional income and the cost of doing it. If you gave a credit or discount, use the figure you actually received rather than pretending the original quotation still happened exactly as planned.

Then put a value against the real labour used on the job, including your own time. That last part matters because if you treat your own labour as free, almost every job can be made to look profitable.

Look at what changed from the price

Job costing becomes useful when you understand why the actual result differed from your price. If you allowed eight days and the job took ten, look at what used the extra time.

Perhaps something genuinely hidden appeared after strip-out. Maybe the customer changed something. Another trade might have held the programme up, or perhaps the installation simply takes longer than you have been allowing for.

Those are different problems and they need different responses. If you missed something at survey, improve the survey. If you repeatedly underestimate a certain type of work, change the amount of time you allow. If customers are adding work without it being charged properly, fix the way you deal with additional work. Looking backwards should change what you do forwards.

Count the small bits of time as well

This is an area where tradespeople can give away a surprising amount without noticing. You collect a replacement part on the way home. You call back for an adjustment. You spend an hour sorting out a damaged product. You pop back because something will only take ten minutes.

Good service is part of running a professional installation business, and I am not suggesting every small thing becomes another invoice. But the time still happened.

If the same type of job repeatedly needs extra visits, collections or remedial work, you need to know. Otherwise you will price the next one as though none of those things ever happen.

One extra hour on one job does not look particularly important. Repeated across dozens of jobs over a year, it can become a very different number.

The job can look different once everything is included

Suppose you priced an installation on the basis of eight days. It actually used ten, one subcontract cost more than expected and you made another half-day visit after completion.

The customer may still have paid the full quoted price and the bank account may still look as though plenty of money came in. The question is what was left after the extra time and costs were recognised. That is the number that tells you whether the original price worked.

This is something I wish I had looked at much more closely earlier in business. For a long time, the bank balance, whether the bills were paid and whether there was money put aside for tax were a large part of how I judged how things were going.

As the business grew, that became less useful. More jobs, more teams and more money moving through the business could make everything look healthy while individual jobs were quietly using more time and money than expected. Being busy can hide quite a lot.

For a simple worked example, take £6,000 of job income excluding VAT, £1,800 of materials and other direct costs, 10.5 days of your own labour valued at £250 a day, and overheads recovered at £100 a day. That leaves £525: £6,000 minus £1,800, £2,625 and £1,050. The job has left 8.75% of its income after those allowances, before tax. These are example figures, not suggested rates. Your own labour allowance helps you judge the job commercially; it does not make sole-trader drawings a deductible wage in your tax accounts.

Look for patterns rather than worrying about one job

Every installer will have jobs that go wrong financially from time to time. Something unexpected happens, you make a mistake or a product problem turns a straightforward installation into a headache. One bad job does not necessarily mean your whole pricing system is wrong. The useful information appears when you start seeing the same thing repeatedly.

If bathrooms are regularly taking longer than you allow, that is telling you something. If one source of work consistently needs unpaid return visits, that is telling you something. If additional work keeps being carried out without being properly agreed and charged, that is telling you something as well.

I would keep the review simple enough that you actually do it. Compare the final income with the actual direct costs and the real labour used, allow for the business costs in the same way you did when pricing the work, and see what was left.

Compare that result with what you expected and understand any difference before you price the next similar job. Over time, your own completed installations become one of the best pricing guides you have because they belong to your business, your customers and the way you actually work.

The Every Install Profit Planner inside Free membership can help you look at the wider numbers in the business.

If the review shows that the problem began with the original quotation, go back to How to Price a Job. If the main difference was your time, read How to Work Out Your Day Rate. And if the diary is full but the money still does not seem to match the amount of work you are doing, read Why Am I Busy All the Time but Still Not Making Enough Money?


By Mark Conacher

Mark spent more than 20 years on the tools in kitchen and bathroom installation and nearly 30 years building and running an award-winning installation business. He founded Every Install to provide practical help with the business side of installation — the part most of us were never really taught.

Learn more about Mark Conacher →

Building More Than Just An Installation Business

EveryInstall.com part of Every Trade Pro

Get practical insight and Every Trade Pro updates delivered straight to your inbox.

    Privacy Preference Center